Plan Construction
Overview
Plan construction takes a design you've placed on a site and shows how it would be built:
- the ground, and how much earth is cut and filled;
- what comes down first;
- how trucks and the crane get in, and a rough programme;
- a cost plan by element;
- what the building code asks of each building;
- your own products in the embodied carbon.
Everything is an estimate for early planning, with its source. A surveyor, a geotechnical engineer, a building surveyor and a quantity surveyor confirm it. Nothing here is advice to build, and nothing says the design complies.
Opening It
In Build, place your buildings and save the scenario. Then, in step 4 (Take it further), choose Plan construction.
The panel has a tab for each part. With more than one site, pick the site at the top. It reads the saved design: save your changes, then Measure again.
While it's open, the map shows:
- cut and fill, shaded on the lot (orange is cut, blue is fill; deeper is darker);
- where retaining is needed;
- the buildings that come down (dashed);
- the way in, laydown (green), hoarding (amber) and the crane's swing (dashed).
Ground
The ground across the lot comes from the best surface there is:
- your drone capture's ground model;
- else the City of Melbourne's 1 m elevation model;
- else Geoscience Australia's 5 m model from LiDAR.
For each building:
- Floor level: 150 mm above the ground at its entrance. Type your own in the box (m AHD). To go back, empty the box or choose Use the ground's level.
- Basements: add up to 3 levels in Build, on the selected building (Basement levels). Each is 3.0 m, with a 300 mm slab. The car spaces they hold are counted from their area, and the feasibility uses them.
- Cut and fill: in cubic metres, for each building and for the site. Also the spoil to take away (×1.3 for bulking), the fill to bring in (×1.1 for compaction), and truck loads at 10 m³ each.
- Retaining: where a cut of more than 1 m runs within 2 m of a boundary. This needs protection works for the neighbour.
- Flood: on a site in a flood overlay (LSIO, SBO, FO), you're told to set the floors at least 300 mm above the 1% AEP flood level. No open source gives that level, so get it from the floodplain authority (Melbourne Water's flood level certificate in its area) and type it as the floor level.
Demolition
The existing buildings on the site come down unless you keep them (Keep what's here in Build). For each:
- its floors, floor area and volume;
- its age:
- inside the City of Melbourne, from the City's CLUE survey;
- otherwise, from the era you gave the site;
- otherwise, not known;
- its construction (timber and masonry, or concrete from 3 floors);
- whether it's on or near the boundary.
A building from the last five years is flagged: check it's really meant to come down. It may be the approved building itself, built since.
What to know first:
- Council: its report and consent to demolish (Building Act 1993, section 29A).
- Heritage overlay: a planning permit to demolish (Clause 43.01-1). A heritage overlay on the lot next door that only meets this site's edge isn't on the site, so it doesn't count (see Overlays in the Check).
- Victorian Heritage Register: a permit from Heritage Victoria (Heritage Act 2017).
- On or within 1 m of the boundary: protection works for the neighbour (Building Act 1993, Part 7).
- Asbestos: a survey before demolition for anything built before 1990, or of unknown age. Asbestos was used in building products until the end of 2003.
Waste and cost:
- waste in tonnes, split by material (brick and concrete, timber, plasterboard, metals and the rest), with indicative shares;
- a cost range per m² of floor area, with brick, concrete, metals and timber recycled;
- plus plasterboard and mixed waste to landfill, at the disposal rate.
Asbestos removal isn't in the cost.
Access and Crane
- Way in: the frontage with the widest road reserve. A reserve under 12 m may be too narrow for a 12.5 m rigid truck to turn in: smaller trucks, or traffic management. A crossover not drawn on that frontage needs council's vehicle crossing permit.
- Laydown: the open part of the site during the build. Under 40 m² means materials on the footpath or road, with council's occupation permit.
- Hoarding: along the street where a building is within 3 m of it.
- The crane:
- Up to 3 storeys: a mobile crane from the street on the day.
- Higher: a tower crane that reaches every building, with its swing drawn on the map. You're told the lots it swings over (the neighbours' consent) and whether it swings over the street (council's permit, and the Department of Transport's on an arterial road).
- Stages: with several buildings, the one farthest from the way in is built first, so the access stays open.
- A rough programme: weeks for demolition, earthworks, footings and slab, structure, fit-out and handover, then the total in months, from the start on site to handover. It's our own estimate, checked against the ABS's average completion times:
- a two-storey house: about 8 months;
- a row of four to six townhouses: 11 to 13 months;
- 5 storeys: about 16 months;
- 40 storeys: about 3 years.
- Use it in the feasibility puts those months in place of the feasibility's default construction time.
Cost Plan
The feasibility's build cost, split by element: preliminaries, substructure, frame and upper floors, external walls and windows, roof, internal walls and finishes, services, fit-out and external works. The split uses typical shares for houses and for apartments, so the total is the feasibility's.
Measured from the site, added on top:
- demolition;
- earthworks;
- retaining;
- site works from the driveways, paths and planting you've drawn.
Some costs are in the feasibility already, so they aren't counted again:
- Basements: where the feasibility prices basement car spaces, their dig and shoring are in that price, so the earthworks are measured as if there were no basement.
- Surface car parks: priced per space in the feasibility, so they aren't in site works.
A part that couldn't be read is said, rather than left out without a word. The figures are the feasibility's own: the options of its last run and your assumptions, so the build is the same as there.
Then fees and contingency, and the total.
- Add these to the feasibility adds the measured lines to the feasibility, as lines of their own.
- Download as a spreadsheet saves the cost plan as a CSV.
The rates are ours, each with its source. To use your own, open Account settings → Your assumptions → Construction rates.
Building Code
For each building, what the National Construction Code 2025 asks:
- its class (Class 1 houses and townhouses, Class 2 apartments);
- its rise in storeys and effective height;
- its type of construction (A, B or C).
What it asks:
- Fire: the fire resistance (FRL) of walls and floors between homes, with the table it comes from (Specification 5).
- Sound between homes: Rw + Ctr 50 for walls and floors; Ln,w + CI 62 for floors.
- Sprinklers: where the code asks for them (over 25 m effective height, or 4 storeys or more of homes).
- Basement car park: Class 7a, fire-separated from the homes above.
- Townhouses in a row (or several homes placed as one building): a separating wall between homes.
Generic systems commonly used to meet each, and a materials schedule under NATSPEC-style headings, including the windows and doors you placed in the façade editor.
It's what the code asks, not that the design complies: a building surveyor decides, with a manufacturer's tested system. The walls by the boundaries are measured in the Check.
Products and Carbon
To use a product you've chosen in place of a material's average:
- Pick the material.
- Give the product's name, its EPD number, its figure (kgCO2e per unit, A1–A3), when the EPD expires and a link to it. Find EPDs at EPD Australasia.
- Choose Keep this product.
Your products are kept on your account, for every scenario. Run Embodied Carbon again and its modelled breakdown, by element and material, uses them. Each is listed there with its EPD, and an expired EPD is marked.
The headline stays Infrastructure Australia's per-m² figure.
The Construction Brief
The Brief tab, or the Construction brief box in the Check's Report tab, puts all of it in one document:
- the ground and cut and fill;
- demolition;
- access, the crane and the programme;
- the cost plan;
- what the building code asks;
- your products.
Make the construction brief keeps it on the server under a link. Only the scenario's owner makes one, as for the other reports shared by link. Then:
- Download the PDF;
- Copy the link: anyone with it can read the brief, without signing in;
- Turn the link off, when you want it to stop opening.
Briefs made before are listed to open again, even with the link off. Opening one doesn't use the month's allowance, and your own openings aren't counted as views. The scenario's owner sees every brief of it and can turn any off. Each brief is in My content, and you can share it with a group.
You can make 3 construction briefs a month. Plan construction on screen stays free.
How It Was Tested
Plan construction was run on approved developments in the City of Melbourne and on the council officers' cases from the permit package's test. What it says was checked against the planning controls and the officer's report. See How We Tested It.
Sources
- Ground: City of Melbourne, VicMap Elevation 1 m; Geoscience Australia, 5 m DEM from LiDAR (CC BY 4.0).
- Building ages: City of Melbourne, Census of Land Use and Employment (CLUE).
- Heritage: Vicmap Planning (heritage overlays); Victorian Heritage Database (the register).
- Flood: Vicmap Planning (flood overlays); the 300 mm freeboard from the Flood Risk model.
- Building code: National Construction Code 2025, Volume One (Specification 5, Parts C, E1 and F7) and the Housing Provisions.
- Programme: our own estimate, checked against the ABS's average dwelling completion times.
- Rates: our own indicative rates, each with its source; the build cost from the feasibility.
- EPDs: the ones you enter, from EPD Australasia.